2007
December 17

Company was founded

Jens Dall breaks the code on how to gasify moist biomass with low emissions. He incepts Dall Energy to bring the new biomass technologies to the market.

CNN_Dall-Energy_Jens_Dall

 

2010
June 7

★ Innovation Award at Expobioenergía

At the Expobioenergía in Valladolid, Spain, Dall Energy was given the innovation award. The award was in the category “Medium to large scale Bioenergy Projects” for the Innovation “Dall Energy Furnace”.

2011
March 31

🏭 Bogense District Heating

8 MW Dall Energy Furnace. The first Dall Energy furnace enters into commercial operation.
May 19

★ The European Inventor Award

At a ceremony in Budapest on the 19th of May 2011 Jens Dall Bentzen was awarded Europe´s highest distinction for inventors. The ceremony was hosted by the European Patent Office and the award was given to Jens Dall Bentzen for the Dall Energy biomass system.   Handshake from Jesper Kongstad, CEO of the Danish Patent Office, with Michel Barnier, EU Commissioner for the Internal Market in the middle.
September 7

★ The Clean Tech Price

The Danish Environmental Agency awarded Dall Energy the Clean Tech Price for their technology that enables more environmentally friendly production of sustainable energy.  
2013
March 20

🏭 Warwick Mills, USA

2 MW Dall Energy biomass plant. Dall Energy furnace enters into commercial operation in dual-purpose industrial application, removing pollutants from ventilation air and providing steam for the industrial process.
2014
September 4

🏭 Sønderborg District Heating

9 MW Dall Energy biomass plant. Dall Energy furnace enters into commercial operation.    
2017
December 14

★ Blue Tech Award

The Dall Energy furnace was selected Bluetech-award winner as a future technology for reducing pollution in China. The award ceremony took place in Beijing on December 14, 2017  
Bluetech-award_500x465_Dall-Energy
2018
July 6

🏭 Sindal District Heating

6 MW CHP plant. Turnkey delivery of complete combined heat & power plant. Plant enters into commercial operation.
2019
March 11

🏭 Contract: Dalkia France

New contract for turnkey delivery of 20 MW furnace in Rouen. Project design and supply are ongoing.